← Back to all articles
Data Centre Electrical

Data Centre Cooling and the Electrical System: Why They're Inseparable

ETES Engineering Team
·
May 31, 2026
Data centre CRAC cooling units and electrical distribution in Thailand

Data-centre design conversations usually split into “power” and “cooling” as if they were separate problems. They aren't. In a Thai data centre — where ambient temperatures make cooling work even harder — the cooling system is one of the largest electrical loads in the building, and it has to be designed hand-in-hand with the power distribution. Here's why.

Cooling is an electrical load — a big one

Every CRAC/CRAH unit, chiller, pump and fan that keeps the white space cool runs on electricity. In many facilities, cooling accounts for 30–40% of total electrical demand. That load sits on the same switchboards, generators and (for critical cooling) UPS systems as the IT equipment. You cannot size the electrical distribution without knowing the cooling load, and you cannot plan cooling without knowing the power available.

Redundancy has to match on both sides

This is the failure that catches people. You can build a beautifully redundant Tier III or Tier IV power path, but if the cooling isn't on an equally redundant electrical supply, your real availability is only as good as the cooling. IT equipment in a sealed hot room overheats in minutes once cooling stops. So critical cooling must be fed from the same redundant (and often generator-backed, sometimes UPS-ridethrough) paths as the IT load — N+1 or 2N to match the tier.

The Thai climate raises the stakes

Bangkok's high ambient temperature and humidity mean cooling systems work harder year-round than in temperate climates — higher continuous electrical load, and less margin when a unit drops out. Design has to account for worst-case ambient, not average.

It all comes back to the switchboard and generators

Mechanical cooling plant ties into the electrical system at the main switchboard, generator and ATS level. Start-up inrush from large chillers and CRAC compressors must be planned so it doesn't trip protection or overload the generator during a transfer. This is exactly why the electrical and ACMV scopes should be coordinated by one engineering team rather than two contractors pointing at each other.

Design them together, from day one

The practical rule: load (including cooling), redundancy and sequencing are decided together at the single-line-diagram stage. ETES delivers data-centre electrical and ACMV-related electrical works as one coordinated scope — main distribution, generator tie-ins, PDU, and the power feeds to the cooling plant — so the two halves of the room never fall out of step.

FAQ

Frequently asked questions

Why can't I just put cooling on normal mains power?

Because if the mains fails, cooling stops and the room overheats within minutes — defeating the redundant IT power you paid for. Critical cooling must share the same generator-backed, redundant supply as the IT load.

How much of a data centre's power goes to cooling?

Commonly 30–40% of total electrical demand, and proportionally more in hot, humid climates like Thailand's. It's too large a load to treat as an afterthought.

Should cooling be on UPS?

At minimum, control systems and some fans need ride-through so cooling restarts cleanly on generator. Higher tiers put more of the cooling chain on protected power. The right answer depends on your tier target and thermal ride-through time.

Who should coordinate cooling and electrical?

One engineering team. The interface — generator sizing for compressor inrush, redundancy matching, sequencing — is where split-contractor projects fail.